1. |
A takes three times as long as B and C together to do a job. B takes four times as long as A and C together to do the work. If all the three, working together can complete the job in 24 days, then the number of days, A alone will take to finish the job is = ? |
A. | 00 days |
B. | 6 days |
C. | 5 days |
D. | 0 days |
Answer» C. 5 days | |