1. |
A takes 50% more time than B to complete a task. If both work together, they take 18 days to complete the task. Accordingly, if B works alone then in how many days will he complete the work? |
A. | 30 days |
B. | 35 days |
C. | 40 days |
D. | 45 days |
Answer» B. 35 days | |