1. |
A takes 10 hours to do a work. B takes 12 hours to do the same works. In how many hours A & B working together will complete the work? |
A. | 12/3 |
B. | 60/11 |
C. | 60/7 |
D. | 10/5 |
Answer» C. 60/7 | |