A takes 10 days less than the time taken by B to finish a piece of work. If both A and B can do it in 12 days, then the time taken by B alone to finish the work is |
A. | 30 days |
B. | 27 days |
C. | 20 days |
D. | 25 days |
Answer» B. 27 days | |