1. |
A system has 12 magnetic tape drives and 3 processes : P0, P1, and P2. Process P0 requires 10 tape drives, P1 requires 4 and P2 requires 9 tape drives.Process P0 P1 P2 Maximum needs (process-wise : P0 through P2 top to bottom) 10 4 9 Currently allocated (process-wise)522Which of the following sequence is a safe sequence ? |
A. | P0, P1, P2 |
B. | P1, P2, P0 |
C. | P2, P0, P1 |
D. | P1, P0, P2 |
Answer» E. | |