MCQOPTIONS
Saved Bookmarks
| 1. |
A site has a unidirectional slope of 30 with horizontal along its longer side. The projected dimensions of the site on the horizontal plane measures 30 m 40 m. Using cut and fill method the site has to be levelled parallel to the horizontal plane. The minimum amount of earth to be excavated in cubic metre is ____________ |
| A. | 463 to 546 |
| B. | 3463 to 3465 |
| C. | 3433 to 3665 |
| D. | 3461 |
| Answer» C. 3433 to 3665 | |