A shopkeeper has a job to print certain number of documents and there are three machines P, Q and R for this job. P can complete the job in 3 days, Q can complete the job in 4 days and R can complete the job in 6 days. How many days the shopkeeper will it take to complete the job if all the machines are used simultaneously ? |
| A. | 4/3 days |
| B. | 2 days |
| C. | 3/2 days |
| D. | 4 days |
| Answer» B. 2 days | |