1. |
A set of 5 jobs is to be processed on a single machine. The processing time (in days) is given in the table below. The holding cost for each job is Rs. K per day.JobProcessing timeP5Q2R3S2T1A schedule that minimizes the total inventory cost is |
A. | T-S-Q-R-P |
B. | P-R-S-Q-T |
C. | T-R-S-Q-P |
D. | P-Q-R-S-T |
Answer» B. P-R-S-Q-T | |