1.

A set of 5 jobs is to be processed on a single machine. The processing time (in days) is given in the table below. The holding cost for each job is Rs. K per day.JobProcessing timeP5Q2R3S2T1A schedule that minimizes the total inventory cost is

A. T-S-Q-R-P
B. P-R-S-Q-T
C. T-R-S-Q-P
D. P-Q-R-S-T
Answer» B. P-R-S-Q-T