1.

A road of 5 km length will be constructed in 100 days. So 280 workers were employed. But after 80 days it was found that only
3
1
km road was completed.
2

Now how many more people were needed to finish the work in the specified time ?

A. 480
B. 80
C. 200
D. 100
Answer» D. 100