1. |
A road of 5 km length will be constructed in 100 days. So 280 workers were employed. But after 80 days it was found that only
Now how many more people were needed to finish the work in the specified time ? |
||||
A. | 480 | ||||
B. | 80 | ||||
C. | 200 | ||||
D. | 100 | ||||
Answer» D. 100 | |||||