A project has six activities (A to F) with respective activity durations 7,5,6,6,8,4 days. The network has three path A-B, C-D and EF. All the activities can be crashed with the same crash cost per day. The number of activities that need to be crashed to reduce the project duration by 1 day is

A. 1
B. 2
C. 3
D. 6
Answer» D. 6