A project has six activities (A to F) with respective activity durations 7,5,6,6,8,4 days. The network has three path A-B, C-D and EF. All the activities can be crashed with the same crash cost per day. The number of activities that need to be crashed to reduce the project duration by 1 day is |
| A. | 1 |
| B. | 2 |
| C. | 3 |
| D. | 6 |
| Answer» D. 6 | |