1.

A project consists of 150 jobs. The expected completion time for each job is given in days. The project has three critical paths with two jobs in common, J and K. In order to finish the project one day early, the completion time should be reduced one day for ?

A. each of the 150 jobs
B. each of the jobs on the three critical paths
C. either Job J or Job K
D. both Job J and Job K
Answer» D. both Job J and Job K