A project consists of 150 jobs. The expected completion time for each job is given in days. The project has three critical paths with two jobs in common, J and K. In order to finish the project one day early, the completion time should be reduced one day for ? |
A. | each of the 150 jobs |
B. | each of the jobs on the three critical paths |
C. | either Job J or Job K |
D. | both Job J and Job K |
Answer» D. both Job J and Job K | |