A piece of work can be done by 16 men in 8 days working 12 hours a day. How many men are needed to complete another work, which is three times the first one, in 24 days working 8 hours a day? |
| A. | 24 men |
| B. | 22 men |
| C. | 23 men |
| D. | 25 men |
| Answer» B. 22 men | |