1.

A piece of work can be done by 16 men in 8 days working 12 hours a day. How many men are needed to complete another work, which is three times the first one, in 24 days working 8 hours a day?

A. 24 men
B. 22 men
C. 23 men
D. 25 men
Answer» B. 22 men