1.

A manufacturing shop processes sheet metal jobs, wherein each job must pass through two machines (M1 and M2, in that order). The processing time (in hours) for these jobs is:MachineJobsPQRSTUM115328271116M26191320147The optimal make-span (in hours) of the shop is:

A. 120
B. 115
C. 109
D. 79
Answer» C. 109