A manufacturing shop processes sheet metal jobs, wherein each job must pass through two machines (M1 and M2, in that order). The processing time (in hours) for these jobs is:MachineJobsPQRSTUM115328271116M26191320147The optimal make-span (in hours) of the shop is: |
| A. | 120 |
| B. | 115 |
| C. | 109 |
| D. | 79 |
| Answer» C. 109 | |