1.

A manufacturing plant, working in 2 shifts of 8 hrs each, produces 30,000 switch boards using a set of 7 workstations in series. The cycle time, in seconds, is

A. 1.1 to 1.4
B. 1.5 to 1.8
C. 1.9 to 2
D. 2.1 to 2.4
Answer» D. 2.1 to 2.4