1. |
A man undertakes to do a work in 150 days. He employs 200 men. He finds that only a quarter of the work is done in 50 days. How many additional men should he employ so that the whole work is finished in time? |
A. | 75 |
B. | 85 |
C. | 100 |
D. | 120 |
Answer» D. 120 | |