A man undertakes to do a certain work in 150 days. He employs 200 men. He finds that only a quarter of the work is done in 50 days. The number of additional men that should be appointed so that the whole work will be finished in time is = ?

A. 5
B. 00
C. 25
D. 0
Answer» C. 25