| 1. |
A labourer can do a job in 50 hours. After 5 hours he takes a break. What fraction of the job is yet to be done? |
| A. | 0.8 |
| B. | 0.5 |
| C. | 0.75 |
| D. | 0.9 |
| Answer» E. | |