| 1. |
A job can be complete by 12 men in 12 days. How many extra days will be needed to complete the job if 6 men leave after working for 6 days ? |
| A. | days |
| B. | days |
| C. | 2 days |
| D. | 4 days |
| Answer» C. 2 days | |