A is 3 times faster than B. If A can finish a work 32 days less than that of B, find the number of days need to finish the work if both are working together? |
| A. | 12 days |
| B. | 24 days |
| C. | 32 days |
| D. | 16 days |
| Answer» B. 24 days | |