1. |
A is 1.5 times efficient as B therefore takes 8 days less than B to complete a work. If A and B work on alternate days and A works on first day, then in how many days the work will be completed? |
A. | 17 |
B. | 19 |
C. | 19.5 |
D. | 21 |
Answer» C. 19.5 | |