1.

A front-end loader on a given job moves a load of 1.5 m3 of loose soil in one cycle consisting of loading-lifting-travelling-unloading-return trip-and-ready for next loading. If each cycle time is 1.2 minutes, the actual output will be

A. 75 m3/hour
B. 70 m3/hour
C. 65 m3/hour
D. 60 m3/hour
Answer» B. 70 m3/hour