MCQOPTIONS
Saved Bookmarks
| 1. |
A dummy activity is used in PERT network to describe the_____________________? |
| A. | Precedence relationship |
| B. | Resource idleness |
| C. | Resource restriction |
| D. | Necessary time delay |
| Answer» B. Resource idleness | |