1.

A does 80% of a work in 20 days. He then calls in B and they together finish the remaining work in 4 days. How long B alone would take to do the whole work?

A. 12.5 days
B. 100 days
C. 22.5 days
D. 35 days
Answer» C. 22.5 days


Discussion

No Comment Found

Related MCQs