A does 80% of a work in 20 days. He then calls in B and they together finish the remaining work in 4 days. How long B alone would take to do the whole work? |
| A. | 12.5 days |
| B. | 100 days |
| C. | 22.5 days |
| D. | 35 days |
| Answer» C. 22.5 days | |