MCQOPTIONS
Saved Bookmarks
| 1. |
A does 80% of a work in 20 days. He then calls in B and they together finish the remaining work in 3 days. How long B alone would take to do the whole work? |
| A. | 23 days |
| B. | 37 days |
| C. | 37 1/2 days |
| D. | 40 days |
| Answer» D. 40 days | |