| 1. |
A does 75% of a work in 50 days. He then calls in B and they together finish the remaining work in 10 days. How long B alone would take to complete the whole work? |
| A. | 200 days |
| B. | 50 days |
| C. | 100 days |
| D. | 125 days |
| Answer» D. 125 days | |