1. |
A does 4/5th of a work in 20 days. He then calls in B and they together finish the remaining work in 3 days. How long B alone would take to do the whole work? |
A. | 23 days |
B. | 37 days |
C. | 37 ½ days |
D. | 40 days |
Answer» D. 40 days | |