1.

A crew consisting of two carpenters and one helper can fix 10 m2 of a slab form work in 8 hours and the hourly labour rate of a carpenter is Rs. 85 and for a helper is Rs. 69.50. An average hourly rate per worker of the crew will be nearly

A. Rs. 90
B. Rs. 80
C. Rs. 70
D. Rs. 60
Answer» C. Rs. 70