MCQOPTIONS
Saved Bookmarks
1. |
A contractor was engaged to construct a road in 16 days. After working for 12 days with 20 labours it was found that only$${\frac{5}{8}}$$ thof the road had been constructed. To complete the work in stipulated time the number of extra labours required are ? |
A. | 6 |
B. | 2 |
C. | 0 |
D. | 8 |
Answer» B. 2 | |