A contractor was engaged to construct a road in 16 days. After working for 12 days with 20 labours it was found that only$${\frac{5}{8}}$$ thof the road had been constructed. To complete the work in stipulated time the number of extra labours required are ?

A. 6
B. 2
C. 0
D. 8
Answer» B. 2