

MCQOPTIONS
Saved Bookmarks
1. |
A contractor undertook to finish a work in 92 days and employed 110 men. After 48 days, he found that he had already done $$\frac{3}{5}$$part of the work, the number of men he can withdraw so that his work may still be finished in time is ? |
A. | 5 |
B. | 0 |
C. | 5 |
D. | 0 |
Answer» E. | |