1.

A contractor undertook to finish a certain work in 124 days and employed 120 men. After 64 days, he found that he had already done 2/3 of the work.
How many men can be discharged now so that the work may finish in time ?

A. 48
B. 56
C. 40
D. 50
Answer» C. 40