1. |
A contractor undertook to finish a certain work in 124 days and employed 120 men. After 64 days, he found that he had already done 2/3 of the work.
|
A. | 48 |
B. | 56 |
C. | 40 |
D. | 50 |
Answer» C. 40 | |