1.

A contractor undertook to finish a certain work in 124 days and employed 120 men. After 64 days, he found that he had already done 2/3 of the work. How many men can be discharge now, so that the work finish in time ?

A. 40
B. 50
C. 48
D. 56
Answer» E.