A contractor undertakes to make a road in 40 days and employs 25 men. After 24 days, he finds that only one-third of the road is made. How many extra men should he employ so that he is able to complete the work 4 days earlier ? |
A. | 00 |
B. | 0 |
C. | 5 |
D. | one of these |
Answer» D. one of these | |