A contractor undertakes to construct a road in 25 days and engages 28 workers. After 18 days he find that only 2/3 of the work is done. How many more workers he should now engage in order to finish the work in time? |
A. | 36 |
B. | 21 |
C. | 18 |
D. | 8 |
Answer» E. | |