1.

A contractor undertakes to construct a road in 25 days and engages 28 workers. After 18 days he find that only 2/3 of the work is done. How many more workers he should now engage in order to finish the work in time?

A. 36
B. 21
C. 18
D. 8
Answer» E.


Discussion

No Comment Found