

MCQOPTIONS
Saved Bookmarks
1. |
A contractor takes a contract to complete a road in 60 days and employed 105 labours. After 25 days, he found that one-third of the work is completed. How many more labours he required to complete the remaining work in time? |
A. | 75 |
B. | 105 |
C. | 150 |
D. | 45 |
Answer» E. | |