1. |
A Contractor employed a certain number of workers to finish constructing a road in a certain scheduled time. Sometime later, when a part of work had been completed, he realised that the work would ge |
A. | 10 % |
B. | 14 2/7 % |
C. | 20 % |
D. | Can't be determined |
Answer» C. 20 % | |