1.

 A Contractor employed a certain number of workers to finish constructing a road in a certain scheduled time. Sometime later, when a part of work had been completed, he realised that the work would ge

A. 10 %
B. 14 2/7 %
C. 20 %
D. Can't be determined
Answer» C. 20 %