| 1. |
A contractor employed 210 men to build a house in 60 days. After 12 days, he was joined by 70 more men. In how many days will the remaining work be finished? |
| A. | 35 |
| B. | 36 |
| C. | 38 |
| D. | 40 |
| Answer» C. 38 | |