1.

A contract is to be complete in 92 days and 234 men were set to work, each working 16 h a days. After 66 days, 4/7 of the work is completed. How many addition men may be employed, so that the work may be completed in time, each man now working 18 h a day?

A. 162
B. 234
C. 262
D. 81
E. None of the above
Answer» B. 234