1.

A completes 80% of a work in 20 days. Then B also joins and A and B together finish the remaining work in 3 days. How long does it need for B if he alone completes the work?

A. 37 ½ days
B. 22 days
C. 31 days
D. 22 days
Answer» B. 22 days