1.

 A complete 80% of a work in 20 days. Then B also foins and A and B together finish the remaining work in 3 days. How many days will be required for B if he al0one complete the work?

A. 35 Days
B. 30 Days
C. 37 1/2 Days
D. 25 Days
Answer» D. 25 Days


Discussion

No Comment Found