

MCQOPTIONS
Saved Bookmarks
1. |
A complete 80% of a work in 20 days. Then B also foins and A and B together finish the remaining work in 3 days. How many days will be required for B if he al0one complete the work? |
A. | 35 Days |
B. | 30 Days |
C. | 37 1/2 Days |
D. | 25 Days |
Answer» D. 25 Days | |