*/*_A complete 7/10 of a work in 15 days, then he completed the remaining work with the help of B in 4 days. In how many day A and B can complete entire work together?? |
| A. | 10 1/2 days |
| B. | 12 2/3 days |
| C. | 13 1/3 days |
| D. | 8 1/4 days |
| Answer» D. 8 1/4 days | |