1.

A certain number of men can complete a task in 18 days, working 8 hours a day. If the number of men is increased by \(33\frac{1}{3}\%\) and the time spent is decreased by 50%, then in how many days, will the same work be completed?

A. 24
B. 27
C. 30
D. 32
Answer» C. 30