A can finish a work in 24 days, B in 9 days and Dc in 12 days. B & C start the work but are forced to leave after 3 days. The remaining work done by A in- |
A. | 8 Days |
B. | 10 Days |
C. | 6 Days |
D. | 12 Days |
Answer» C. 6 Days | |