A can finish a work in 24 days, B in 9 days and C in 12 days. B and C start the work but are forced to leave after 3 days. The remaining work was done by A in :

A. 5 days
B. 6 days
C. 10 days
D.
E. <table><tr><td rowspan="2">10</td><td style="border-bottom:1px solid #000000;vertical-align:bottom;padding-bottom:2px;"><center>1</center></td><td rowspan="2">days</td></tr><tr><td style="text-align: center;">2</td></tr></table>
Answer» D.