| 1. |
A can do as much work in 4 days as B can do in 5, and B can do as much work in 6 days as C in 7. In what time will C do a piece of work which A can do in a week ? |
| A. | 10 5/24 days |
| B. | 4 4/5 days |
| C. | 6 8/15 days |
| D. | 12 6/19 days |
| Answer» B. 4 4/5 days | |