A can do a work alone in 11 days while B takes 16.5 days to do it alone. It takes 5.5 days for them to complete the work together with C. If C and D can work together in 22 days, then how many days will D need to complete the work alone? |
A. | 44 |
B. | 66 |
C. | 55 |
D. | 77 |
Answer» C. 55 | |