1. |
A can do a piece of work in 9 days and B in 18 days. They began the work together but 3 days before the completion of work A leaves. The time taken to complete the work is: |
A. | 5 days |
B. | 8 days |
C. | 7 days |
D. | 11 days |
Answer» C. 7 days | |