| 1. |
A can do a piece of work in 8 days and B can do it in 10 days seperately. How many days would it take for both A and B to finish the same work together? |
| A. | 33/8 |
| B. | 40/9 |
| C. | 41/10 |
| D. | 42/11 |
| Answer» C. 41/10 | |