A can do a piece of work in 60 days. He works for 15 days and then B alone finishes the remaining work in 30 days. The two together can finish the work in:(INFOTECH COMPANY) |
| A. | 25 days |
| B. | 24 days |
| C. | 32 days |
| D. | 30 days |
| Answer» C. 32 days | |