| 1. |
A can do a piece of work in 4 days. B can do it in 5 days. With the assistance of C they completed the work in 2 days. Find in how many days can C alone do it? |
| A. | 10 days |
| B. | 20 days |
| C. | 5 days |
| D. | 4 days |
| Answer» C. 5 days | |